Watch a live video stream of construction activities at the UIP

July 27, 2018

Demolition of the Maryland Theatre's former box office and courtyard are complete, and contractors are excavating along Potomac Street for the foundation system for the new entry hall building.  Contractors are also working at the rear of the Theatre, installing new storm drainage and sanitary sewer lines.  Interior demolition and abatement activities are continuing in the building to be demolished and replaced by the proposed five-story Barbara Ingram School for the Arts expansion.  Beginning the week of August 13th, contractors will begin the process of installing an underground conduit system in Rochester Place (to the rear of these buildings) that will allow for removal of all of the overhead wires in the future plaza area behind the District Court building.