Hagerstown Citywide Collection System Rehabilitation

12-06-2010 - Citywide Sanitary Sewer Rehabilitation Project Update

Crew from Miller Pipeline Corporation will be arriving on site Monday 12-06-10 to begin by-pass setup for the line segments at the end of Grand Oak Drive (from manholes 12018 to 12017 and 12016 to 12015 to 12014). Install will begin on both of those segments Thursday 12/09/10 and Friday 12/10/10.

Monday 12-13-10 - Crews will be removing the by-pass from the end of Grand Oak and moving it to the line segments at the top of Grand Oak (manholes 12048 to12040 to 12179 to 12035). Crews are scheduled to line those segments beginning 12/15/10, they will be removing bypass pumping after lining is completed.

Customers impacted by the lining will be notified by Miller Pipeline, they will hang door tags, requesting customers conserve water during the lining process.

We do not foresee any other work being completed on this project prior to the New Year.

11-18-10 - Miller Pipeline Corporation is schedule to complete lining on Thursday on segment 7027-7026 (East Franklin & Mulberry Street Intersection). This will be performed at night due to SHA restrictions. Dwayne has procured both the City and SHA permits.

11-19-10 - Miller will be performing pre clean and pre CCTV inspections on Friday afternoon for line segments 12048-12040-12179 (Grand Oak Drive Area).

Schedule is subject to change due to weather conditions

Crews will be lining the sanitary sewer lines in the Wareham Alley area on Tuesday, October 26, 2010 - effective customers will be notified by the Lining crews.

Crews will be lining the sanitary sewer lines in the Mills Street area on Wednesday, October 27, 2010 - effective customers will be notified by the Lining crews.


PROJECT PURPOSE: This project is summarized as sanitary sewer rehabilitation at various locations throughout the City, including open cut point repairs of mains & laterals, cured-in-place lining of mains, sewer lateral lining utilizing the LMK T-Liner process with vacuum excavated cleanouts, manhole rehabilitation and construction of new manholes. The purpose of this work is to eliminate Inflow and Infiltration (I/I) from our Collection System, thus eliminating unwanted groundwater and runoff from the treatment process.

PROJECT AREAS: The rehabilitation will take place in four (4) sanitary sewer districts including:
District # 7 – includes areas between Washington Street, Franklin Street and Potomac Avenue
District # 8 – includes areas between Prospect Street and Summit Avenue
District # 9 – includes Manor Drive, Radcliff Avenue, Tracy’s Lane, Cleveland Avenue, Cannon Avenue, Memorial Blvd, Mill Street, Antietam Street and Dual Highway.
District # 12 – includes Grand Oak Drive, areas between Kenly Avenue and Luther Drive and areas between South Potomac Street and Maryland Avenue.

PROJECT BUDGET: The project was budgeted is $3,050,000 - $1,422,560 ARRA Grant Funding, $800,000 Bay Restoration Grant Funding and $827,440 in 0% interest free loan from MDE.

CONTRACTOR: Miller Pipeline Corporation was awarded the contract.

PROJECT SCHEDULE: The approximated starting date for construction is April 26, 2010. The project scheduled completion date is approximately November 1, 2010.

PUBLIC NOTIFICATION: The contract and their sub-contractors will deliver notification to the residents approximately 48 hours before beginning work in affected neighborhoods. The sub-contractors may request residents to conserve sanitary sewer discharges during short periods of time when the contractor is working in a specific neighborhood. We will continually update the website when there are new events to report.

TRAFFIC DETOUR & Road Closures: The traffic control will change over the course of the project. Detours will be posted accordingly and the City will make every effort to keep the streets open to residents, most of these tasks will be completed within a 24 – 48 hour period and should not require any long term detours or road closures.

Last revised 12/6/2010